Project Mission

At Indus Dyeing Limited, our mission was to implement a sustainable energy solution that aligns with our commitment to environmental stewardship and cost efficiency. By opting for a 500kW on-grid solar system, we aimed to significantly reduce our carbon footprint, lower energy costs, and set a precedent for sustainable practices within the industrial sector. This project reflects our dedication to corporate social responsibility and our proactive approach towards mitigating climate change.

 

The Challenge Of Project

Project Information
Clients:
M/S. Indus dyeing Limited
System Size:
500 kw
System Type:
Hybrid
Location:
korangi
Unit Production Per Month:
60000
Unit Production Per Year:
720000
Monthly Saving:
3300000
Annual Saving:
39,600,000
CO2 Reduction Per year
684 ton
Project Completion Timeline:
30 days
Category:
Industrial