Cart Total Items (0)

Cart

  • Mon - Fri 8:00 - 18:00 / Sunday 8:00 - 14:00
  • Visit Us:
Play Video
Play Video
Growth Solution

Project Mission

In Korangi, our mission was to provide Mr. Irfan with a sustainable energy solution that not only reduced his carbon footprint but also generated substantial savings on his electricity bills. We aimed to install a 10kW on-grid solar panel system efficiently within a 15-day timeline, ensuring seamless integration with his existing setup while maximizing energy production.

 

The Challenge Of Project

Project Information
Clients:
Mr Irfan
System Size:
10 kw
System Type:
On-Grid
Location:
Korangi
Unit Production Per Month:
1,200
Unit Production Per Year:
14,400
Monthly Saving:
66,000
Annual Saving:
792,000
CO2 Reduction Per year
13.68 ton
Project Completion Timeline:
15 days
Category:
Residential